Hydrostatic Testing for Boilers

Hydrostatic Testing for Boilers

April 11, 2017

Hydro testing a boiler is one way to check that you have proper seals on the tubes, flanges, fittings, and connections. This test takes place on new boilers or after any major pressure vessel work.

To begin the test, a hydro pump is used to help fill the boiler with water. The water is pumped into the vessel to the maximum allowable working pressure (M.A.W.P.) and brought to 1.5 x the M.A.W.P.

It is recommended to not use cold water to hydro test a boiler. If you use cold water it will cause the metal tubes to shrink and leak. It is best to let the water sit for approximately 24 hours before performing the test so the water will warm up.

After the boiler is filled with water it will be inspected for leaks. If the boiler has any leaks, the needle on the gauge will drop. A service company will typically perform the hydro test and a technician will sign off that the boiler has either passed or failed the inspection.

Hydro testing is a safe way to check that your boiler is free from any pinhole leaks and cracks. LEL offers a Boiler Reconditioning Program or hydro testing on any boiler that you purchase from us.

Please check out our Youtube channel to watch us hydro a 200 HP Hurst boiler.


We Are LEL

WHY SHOULD I WORK WITH LEL?

Our business is buying, selling and decommissioning but our foundation is people.

You are first. Always. We seek to serve you with integrity, honesty, and the utmost customer service.

Our approach is different. Relationship over transaction. We are committed to embracing the challenge until we have the best solution for you.

WE ARE LEL.

Back to General Posts